10 September 2020

Works commence

07 December 2020

Works update

We are now working outside the Haskins Garden Centre using three-way lights to control traffic movement through our works. We are manning the lights seven days a week between the hours 07:00 and 18:30 to help alleviate any traffic issues that they might cause. We will be working in this area until the Christmas break.

When we return in the New Year, we will be starting work in the area of Newchapel Cricket ground using two-way lights to control traffic flow through the site.


01 March 2021

West Park Road closure

We will be putting in place a road closure on West Park Road from 1 March 2021 for approximately 6 weeks. 

We will maintain access for residents and businesses (and will be operating as usual during the closure period as per government guidance). The closure will affect the A22 end of West Park Road, where no access will be permitted, therefore those who wish to access West Park Road, will need to via the B2037 Haskins Garden Centre end.

All traffic management arrangements and diversions will be advertised on our website at seswater.co.uk/westparkroad and advance warning signs will be visible in the affected areas well in advance of any closures being implemented.

30 April 2021

A22 end of West Park Road re-opened

We've had to extend the original closure length to avoid having to implement a further closure later in the year.

17 December 2021

Works update

Unfortunately, due to unforeseen engineering difficulties, we are having to extend our work completion date into next year. We are currently in discussion with Surrey County Council about this and will provide further updates in due course. We are very sorry for the continued disruption caused.